Standard Progress of Construction Kitchen Remodel

https://www.revivedesignandrenovation.com/wp-content/uploads/2022/10/BeforeAfterAugustine.mov

Kitchen Design and Renovation Construction Progress

Revive Design and Renovation assigns an expert project manager to each remodel site to ensure your project runs as efficiently and smoothly as possible. Our clients are updated daily on the progress of work so they can maintain a stress-, hands-off approach throughout the project. Our quality control processes and professional project management ensures that our clients receive five star quality craftsmanship and a superior customer service experience!

Standard Progress of  Kitchen Design and Renovation Construction

Step 1: Demolition

Our team will  typically demo the entire project in two days. We provide trailers and haul away all materials. We do not leave dumpsters on site, but instead haul away and dispose of all waste.

Step 2: MEP Rough-In (mechanical, electrical and plumbing)

During this time our team is moving all the plumbing and electrical needed. The timelines for this process vary greatly depending on the scope of work and whether or not the job is permitted and we need inspections.

Step 3: Flooring

If applicable we may be laying down new flooring for you. Timelines simply depend on the amount of work to be performed. Specialty patterns such as a herringbone design may lengthen the time needed to complete installation. *Please note that we may lay flooring after the cabinets are installed depending on the type of flooring.

Step 4: Cabinets Installation

This process can often take a week depending on the amount of cabinetry. There is typically a cabinetry punch list to be completed at the end of the project along with other punch list items. 

Step 5: Countertop Installation

It usually takes 10-14 days for the countertop fabricators to measure the countertop template, fabricate and install the countertops. There will not be much other work going on during this time besides waiting for the countertops as they are necessary to complete much of the remaining work. 

Step 6: Trim out

Paint, backsplash, plumbing and electrical fixture installation, etc.

Step 7: Punch List

We create a final punch list with the client and complete 100% of the scope of work to leave you with a beautiful new space!